Discovery Clean Water Alliance Construction Projects

The Discovery Clean Water Alliance is embarking on several construction projects designed to improve the operations of the Salmon Creek Wastewater Treatment Plant and better serve the surrounding community. Construction is slated to begin on the first of three projects this spring, leading immediately into two others through 2024.

Construction Activities and Possible Impacts

Construction will usually be limited to the hours of 7:00 a.m. to 7:00 p.m., Monday through Friday. However, some evening and weekend work may be required.

Contractor vehicle access to the Plant will occur via NW McCann Road.

Construction and contractor materials and equipment will be stored on site at the Treatment Plant.

Parking for construction workers will be at the Treatment Plant.

Traffic bringing workers and materials into the Treatment Plant will increase during this period, with levels varying based on the work planned for any particular day. Construction management staff will be on-site to ensure that the Contractor is in compliance with County standards for hours of operation and noise.

To stay up to date about construction activities, as well as other plant related information, including our annual open houses, please sign up for our e-mail list below.


Subscribe to our mailing list

* indicates required

Questions or Concerns?

Thomas Lebo

Contact:
Thomas Lebo, Alliance Construction Program Manager